Hi,
the documentation on this is very scant, I'm wondeing if anyone has pounded on this and gotten it figured out?
When I create a baseline group and include vmtools upgrade and also vm hardware upgrade, and then try to remediate - it fails. Does not do either, and the error message says to hunt through logs to find cause.
But - if I remediate only vmtools upgrade baseline, it works. And, if I only use vm hardware upgrade, it also works as long as the vm is powered off.
I was led to believe that we could create a baseline group that includes both baselines, and that when remediation occured it would first do vmtools, then restart and complete hardware upgrade.
Is this not actually possible?